What To Expect

Completing a renovation of any kind can often be a stressful process, mainly due to the disruption to your normal routine and the worry that things won’t be as you expect them. We know it’s better to be eyes wide open about a project so you know what to expect.

Kitchen Craftsmen kitchen cabinet door profile comparison renovation

1. Choosing Your New Kitchen

Timescale: 5 – 10 days

DESIGN AND QUOTE
Once we have a copy of your builder plans or an accurate plan of your kitchen space we can discuss what you would like, any layout changes you want to make, design your new kitchen and provide a written estimate. This usually takes 5 days but we are always happy to try and work to your time scale. In addition to this, if you prefer we are able to visit your home and carry out a site survey.

CHECK MEASURE
If you have supplied the kitchen measurements, then we will always carry out a check measure once you have paid your deposit. With these measurements we then revise the kitchen design if required and provide you with a final quotation for your cabinetsbenchtops and fittings.

At this point we can also provide an estimate on plumbing and electrical work, flooring, tiling, appliances and other finishes for those clients who would like us to take care of everything. Otherwise we will arrange and manage the trades and allow you to pay them directly.

PRE-RENOVATION
A few days before we are due to start work at your property our project liaison will contact you by telephone or email to introduce the installation team. They will be responsible for your installation project and can be contacted with any questions you may have. They work closely with your designer to ensure things go smoothly.

2. Let's Get Renovating!

Timescale: 5 – 21 days subject to specification

DAY 1 – DISCONNECTING PLUMBING AND ELECTRICS
This is where the ‘fun’ starts! You can’t have a new kitchen without the old being taken out and this can’t happen until the plumber and electrician visit and temporarily disconnect the water and electricity. Where possible, any new pipes or wiring will also be carried out on this day.

DAY 2 – REMOVING YOUR OLD KITCHEN AND DELIVERY OF NEW CABINETS
Once the services are disconnected, the old kitchen cabinetry is removed and disposed of. This precedes any building work that is required such as removing walls or bulkheads. An average size kitchen can take several hours to remove and can include tile removal too.

Kitchen Craftsmen Kitchen Remodeling Perth

We also deliver your new kitchen cabinets on this day and will store them in the empty kitchen area if possible, to reduce the disruption to your home. It is very worthwhile to be at home to receive your new kitchen and to sign the delivery documents.

Kitchen Craftsmen kitchen renovation perth

DAY 3 – INSTALLING YOUR NEW KITCHEN
The real work begins when one of our fully qualified and experienced installers begins to bring your new kitchen to life. Working with the agreed plan they will carry out the required work. This will involve the usual noise, sawdust and disruption that you would expect but the end result is always worthwhile and our installers are professional, friendly and hardworking.

DAY 4 – INSTALLING YOUR NEW KITCHEN / RECONNECTING ELECTRICS AND PLUMBING
Depending on the size and complexity of the project, the installer will be with you for up to 2 days, sometimes 3. The last day with the installer is usually when the doors go on, laminate benchtops are fitted and adjustments are made. It can also be when the plumber and electrician returns to reconnect your services. Then the kitchen is useable again!

DAY 5 – STONE BENCHTOP TEMPLATE
If you have specified stone benchtops we will need to make a template only once the cabinets are fitted. Using specialised digital measuring equipment we take an accurate image of the benchtop area and then get to work making your new stone tops. The measuring takes about 1 hour and is usually either on the final day of cabinet installation or the next available working day.
It is very important to note that during manufacturing time, your sink and cooktop will not be useable. If you have limited access to washing and cooking elsewhere – we can install temporary benchtops and temporarily connect water and electricity. This costs a little more of course as it requires additional visits from the plumber and electrician. Please tell us in advance if you want this service.

DAY 14 – INSTALL STONE BENCHTOPS
Approximately 10 working days after we have completed the template, your new stone benchtops are ready to install. We arrange a morning or afternoon appointment with you and the installation can take up to 3 hours subject to size and complexity. Once they are fitted, your kitchen really does start to look like the beautiful room you had been working towards!

Kitchen Craftsmen Client Renovation Project Perth1

DAY 15 – RECONNECT WATER AND ELECTRICS
Once the stone benchtops are installed, the cooktop and sinks can be fitted and connected. This is when they become ready to use and enjoy. Your kitchen renovation is now complete…unless of course you are decorating, changing your flooring or adding a splashback!

Final Day - Handover

Once we have completed the agreed renovations including any snag items that can occur, we will complete our inspection paperwork and request final payment. Once this is received we issue your warranty and leave you to enjoy your new kitchen. But of course we are always available to help with normal adjustments or to give you advice on how to care for your kitchen.

Kitchen Craftsmen celebrating new kitchen

Welcoming Showrooms

The Kitchen Craftsmen difference is apparent from the moment you step foot in one of our five showrooms. For a start, all our team are experienced designers, who can listen to your desires, needs and budget requirements and transform them into the kitchen of your dreams – from the initial consultation right through to installation.

Get in touch with us

"*" indicates required fields

First Name**
Last Name*
This field is for validation purposes and should be left unchanged.